Assessment Year | 2002 |
---|---|
Principal Product | Activation Carbon |
NAICS |
n/a
|
SIC | 2898: |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
8,700,000
ft2
|
Annual Production | 90,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $311,726 | 9,832,800 |
kWh
|
$0.032 |
Electricity Demand | $130,222 | 25,685 |
kW-mo/yr
|
$5.07 |
Electricity Fees | $(-4,547.0) | - |
|
- |
Natural Gas | $583,892 | 129,426 |
MMBtu
|
$4.51 |
Fuel Oil #1 | $39,989 | 30,761 |
MMBtu
|
$1.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $367,509 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $362,373 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $306,746 | $5,202 |
$306,746
9,380,615
kWh
|
- | - | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $26,355 | - |
$10,069
307,914
kWh
|
$16,286
-
kW-mo/yr
|
- | - | - | |
03 | 3.4115: Recover and reuse cooling water | $14,779 | $6,925 | - | - | - | - |
$14,779
-
Tgal
|
|
04 | 2.7124: Make a practice of turning off lights when not needed | $9,139 | - |
$5,377
164,427
kWh
|
$3,762
-
kW-mo/yr
|
- | - | - | |
05 | 2.4314: Use synthetic lubricant | $4,592 | - | - | - |
$4,592
-
MMBtu
|
- | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $3,855 | $778 |
$3,855
117,878
kWh
|
- | - | - | - | |
07 | 2.2135: Repair and eliminate steam leaks | $720 | $2,145 | - | - | - | - |
$720
-
Tgal
|
|
08 | 3.5311: Recover and reuse waste material | $762 | - | - | - | - | $762 | - | |
09 | 3.2176: Increase use of automation | $561 | $87 |
$561
17,148
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $367,509 | $15,137 |
$326,608
9,987,982
kWh
|
$20,048
-
kW-mo/yr
|
$4,592
-
MMBtu
|
$762 |
$15,499
-
Tgal
|
||
TOTAL IMPLEMENTED | $362,373 | $12,127 |
$322,192
9,852,956
kWh
|
$20,048
-
kW-mo/yr
|
$4,592
-
MMBtu
|
$762 |
$14,779
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs