Assessment Year | 2001 |
---|---|
Principal Product | Industrial Paperboard Products |
NAICS |
n/a
|
SIC | 2621: Paper Mills |
Sales Range | $10 M to 50M |
# of Employees | 61 |
Plant Area |
80,000
ft2
|
Annual Production | 1,000
ton
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,701 | 1,168,016 |
kWh
|
$0.039 |
Electricity Demand | $21,425 | 2,708 |
kW-mo/yr
|
$7.91 |
Electricity Fees | $2,462 | - |
|
- |
Natural Gas | $25,496 | 3,625 |
MMBtu
|
$7.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,755 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,404 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,587 | $585 |
$3,937
111,720
kWh
|
- |
$1,650
-
MMBtu
|
|
02 | 2.4226: Use / purchase optimum sized compressor | $4,350 | - |
$4,350
123,434
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,597 | $480 |
$1,597
45,320
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $364 | - |
$364
3,600
kWh
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $233 | - |
$233
6,608
kWh
|
- | - | |
06 | 2.3137: Use power during off-peak periods | $210 | - | - |
$210
-
kW-mo/yr
|
- | |
07 | 2.4314: Use synthetic lubricant | $158 | - |
$71
2,019
kWh
|
$87
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $146 | $160 |
$146
4,158
kWh
|
- | - | |
09 | 2.2136: Install / repair insulation on steam lines | $110 | $106 | - | - |
$110
-
MMBtu
|
|
TOTAL RECOMMENDED | $12,755 | $1,331 |
$10,698
296,859
kWh
|
$297
-
kW-mo/yr
|
$1,760
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,404 | $480 |
$2,194
55,528
kWh
|
$210
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs