ITAC Assessment: TA0006
ITAC logo
ITAC Assessment: TA0006
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Leather Goods
NAICS
n/a
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 236
Plant Area 150,000
ft2
Annual Production 2,400,000
ton
Production Hrs. Annual 2,793
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,186 699,936
kWh
Electricity Demand $14,397 3,539
kW-mo/yr
Electricity Fees $6,393 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,062 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.441: Install automatic packing equipment $89,376 $40,000 n/a - - - $89,376 -
02 2.8112: Combine utility meters $9,444 $19,000 - - - - $9,444
03 2.7447: Install vinyl strip / high speed / air curtain doors $2,060 $367 $2,060
30,568
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,518 - $942
13,264
kWh
$576
-
kW-mo/yr
- - -
05 3.5217: Reuse / recycle/ sell paper products $450 $35 - - $450
-
lb
- -
06 2.7135: Install occupancy sensors $114 $124 $114
1,592
kWh
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $100 $3 $100
1,310
kWh
- - - -
TOTAL RECOMMENDED $103,062 $59,529 $3,216
46,734
kWh
$576
-
kW-mo/yr
$450
-
lb
$89,376 $9,444
TOTAL IMPLEMENTED $13,472 $19,402 $3,002
43,832
kWh
$576
-
kW-mo/yr
$450
-
lb
- $9,444
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs