ITAC Assessment: TA0004
ITAC logo
ITAC Assessment: TA0004
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Prefabricated Homes
NAICS
n/a
SIC 2452: Prefabricated Wood Buildings and Components
Sales Range $50
M
to 100
M
# of Employees 236
Plant Area 102,000
ft2
Annual Production 2,490
pieces
Production Hrs. Annual 2,117
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,020 1,129,857
kWh
Electricity Demand $41,857 5,296
kW-mo/yr
Electricity Fees $3,767 -
Natural Gas $15,795 13,775
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $129,244 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $125,299

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 4.652: Replace existing equipment with more suitable substitutes $91,307 $1,161 $(-1,017.0)
(-30,456)
kWh
- $92,324 -
02 3.5311: Recover and reuse waste material $27,800 $35 - $27,800
-
Tgal
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,501 $919 $4,501
134,713
kWh
- - -
04 4.446: Automate finishing process $3,432 $5,220 n/a - - $3,432 -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,267 $1,357 $1,267
37,928
kWh
- - -
06 2.7135: Install occupancy sensors $513 $284 $513
12,994
kWh
- - -
07 4.821: Pay bills on time to avoid late fees $424 - - - - $424
TOTAL RECOMMENDED $129,244 $8,976 $5,264
155,179
kWh
$27,800
-
Tgal
$95,756 $424
TOTAL IMPLEMENTED $125,299 $3,472 $4,751
142,185
kWh
$27,800
-
Tgal
$92,324 $424
Yearly Savings* Imp'd Cost* Electricity Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs