Assessment Year | 1998 |
---|---|
Principal Product | Metal Shop |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
40,000
ft2
|
Annual Production | 33
ton
|
Production Hrs. Annual | 6,300
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,280 | 1,098,183 |
kWh
|
$0.063 |
Electricity Demand | $8,750 | 3,176 |
kW-mo/yr
|
$2.76 |
Electricity Fees | $4,215 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $163,002 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $885 | $60 |
$814
14,947
kWh
|
$71
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7135: Install occupancy sensors | $385 | $675 |
$294
5,275
kWh
|
$91
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,253 | $2,300 |
$1,253
22,860
kWh
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $171 | $261 |
$152
2,931
kWh
|
$19
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7224: Reduce space conditioning during non-working hours | $505 | $675 |
$505
9,379
kWh
|
- | - | - | - | - | |
06 | 3.6192: Use a less expensive method of waste removal | $936 | $60 | - | - |
$936
-
lb
|
- | - | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $603 | $30 | - | - | - | - | $603 | - | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $158,264 | $128,600 |
$(-9,281.0)
(-170,281)
kWh
|
$(-2,555.0)
-
kW-mo/yr
|
- | $(-157,500.0) | - | $327,600 | |
TOTAL RECOMMENDED | $163,002 | $132,661 |
$(-6,263.0)
(-114,889)
kWh
|
$(-2,374.0)
-
kW-mo/yr
|
$936
-
lb
|
$(-157,500.0) | $603 | $327,600 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs