ITAC Assessment: SU0602
ITAC logo
ITAC Assessment: SU0602
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Specialty chemicals
NAICS 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 90,000
ft2
Annual Production 33,865
lb
Production Hrs. Annual 8,008
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $240,230 3,745,487
kWh
Electricity Demand $88,294 6,843
kW-mo/yr
Electricity Fees $8,681 -
Natural Gas $143,033 22,365
MMBtu
Waste Disposal Costs
Water Usage $5,800 40,000
Tgal
TOTAL YEARLY COSTS $486,038
RECOMMENDED SAVINGS* $411,446 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 3.1161: Eliminate/reduce an operation $2,057 - $1,224
19,125
kWh
$1,355
-
kW-mo/yr
- $(-521.6)
-
MMBtu
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,223 - $4,223
65,981
kWh
- - - -
03 2.8114: Change rate schedules or other changes in utility service $32,852 - - - $32,852 - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,297 $15,700 $21,204
331,313
kWh
$14,093
-
kW-mo/yr
- - -
05 2.4221: Install compressor air intakes in coolest locations $2,039 $943 $2,039
31,866
kWh
- - - -
06 2.7144: Install spectral reflectors / delamp $400 $200 $307
4,804
kWh
$93
-
kW-mo/yr
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $829 $483 $829
12,949
kWh
- - - -
08 2.4322: Use or replace with energy efficient substitutes $3,037 $4,295 $1,256
19,622
kWh
$347
-
kW-mo/yr
- - $1,435
09 2.2511: Insulate bare equipment $107 $303 $91
1,424
kWh
- - $16
-
MMBtu
-
10 2.7135: Install occupancy sensors $231 $661 $231
3,604
kWh
- - - -
11 2.7243: Improve air circulation with destratification fans / other methods $1,849 $7,665 $(-221.8)
(-3,465)
kWh
$(-67.7)
-
kW-mo/yr
- $2,139
-
MMBtu
-
12 2.9114: Use solar heat to make electricty $328,524 $3,397,400 $328,524
3,991,473
kWh
- - - -
TOTAL RECOMMENDED $411,446 $3,427,650 $359,706
4,478,696
kWh
$15,820
-
kW-mo/yr
$32,852 $1,633
-
MMBtu
$1,435
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs