Assessment Year | 2025 |
---|---|
Principal Product | Bottled Beverages - water, apple cider, apple/fruit fiber powder, bulk apple juice |
NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
255,000
ft2
|
Annual Production | 23,000,000
units
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $699,074 | 13,885,618 |
kWh
|
$0.050 | |
Electricity Demand | $108,005 | 34,124 |
kW-mo/yr
|
$3.17 | |
Electricity Fees | $30,815 | - |
|
- | |
Natural Gas | $119,157 | 7,688 |
MMBtu
|
$15.50 | |
Other Gas | $49,006 | 1 |
MMBtu
|
$49,006.35 | |
Waste Disposal Costs | |||||
Water Usage | $414,239 | 115,272 |
Tgal
|
$3.59 | |
TOTAL YEARLY COSTS | $1,420,296 | ||||
RECOMMENDED SAVINGS* | $21,989 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,400 | - | - |
$5,400
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,364 | - |
$1,364
27,272
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $299 | $63 |
$299
5,990
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $1,304 | $446 | - | - |
$1,304
-
MMBtu
|
|
05 | 2.4221: Install compressor air intakes in coolest locations | $1,033 | $372 |
$1,033
20,655
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $1,135 | $2,941 |
$1,135
22,705
kWh
|
- | - | |
07 | 2.7234: Use heat pump for space conditioning | $11,453 | $34,327 |
$(-10,483.0)
(-209,664)
kWh
|
- |
$21,936
-
MMBtu
|
|
TOTAL RECOMMENDED | $21,989 | $38,148 |
$(-6,651.9)
(-133,043)
kWh
|
$5,400
-
kW-mo/yr
|
$23,240
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs