ITAC Assessment: SU0564
ITAC logo
ITAC Assessment: SU0564
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Woven fabrics
NAICS 313210: Broadwoven Fabric Mills
SIC 2221: Broadwoven Fabric Mills, Manmade Fiber and Silk
Sales Range $10
M
to 50
M
# of Employees 64
Plant Area 166,000
ft2
Annual Production 700,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $480,031 2,179,200
kWh
Electricity Demand $47,765 4,968
kW-mo/yr
Electricity Fees $2,740 -
Natural Gas $12,356 1,054
MMBtu
LPG $2,555 96
MMBtu
Waste Disposal Costs
Water Usage $1 411
Tgal
TOTAL YEARLY COSTS $545,448
RECOMMENDED SAVINGS* $47,481 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings One-time Revenue or Avoided Cost Savings
01 2.7122: Disconnect ballasts $103 - $82
374
kWh
$21
-
kW-mo/yr
- - -
02 4.821: Pay bills on time to avoid late fees $1,442 - - - - - $1,442
03 2.4239: Eliminate or reduce compressed air usage $3,941 - $3,941
17,914
kWh
- - - -
04 2.2437: Recover waste heat from equipment $3,312 $118 $2,776
12,619
kWh
- $536
-
MMBtu
- -
05 2.4221: Install compressor air intakes in coolest locations $4,420 $332 $4,420
20,090
kWh
- - - -
06 4.651: Install back-up equipment $32,534 $169,100 - - - - $32,534
07 2.7135: Install occupancy sensors $124 $723 $124
562
kWh
- - - -
08 2.8227: Adjust / maintain fork lift trucks for most efficient operation $1,605 $12,000 $(-658.5)
(-2,993)
kWh
- - $2,263
-
MMBtu
-
TOTAL RECOMMENDED $47,481 $182,273 $10,685
48,566
kWh
$21
-
kW-mo/yr
$536
-
MMBtu
$2,263
-
MMBtu
$33,976
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs