ITAC Assessment: SU0538
ITAC logo
ITAC Assessment: SU0538
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Toner and Printer Ink
NAICS 333316: Photographic and Photocopying Equipment Manufacturing
SIC 3861: Photographic Equipment and Supplies
Sales Range $1
M
to 5
M
# of Employees 177
Plant Area 360,000
ft2
Annual Production 1,203,257
lb
Production Hrs. Annual 2,340
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,634,094 26,935,914
kWh
Electricity Demand $603,683 55,075
kW-mo/yr
Natural Gas $265,440 51,052
MMBtu
TOTAL YEARLY COSTS $2,503,216
RECOMMENDED SAVINGS* $53,883 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.3132: Recharge batteries on during off-peak demand periods $6,617 - - - - $6,617
02 2.7122: Disconnect ballasts $6,608 - $6,265
104,419
kWh
$343
-
kW-mo/yr
- -
03 2.4322: Use or replace with energy efficient substitutes $3,300 $407 $2,106
35,100
kWh
$1,973
-
kW-mo/yr
$(-778.5)
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $3,828 $1,591 $3,828
63,801
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $29,330 $15,421 $17,093
284,884
kWh
$4,277
-
kW-mo/yr
- $7,960
06 2.7135: Install occupancy sensors $870 $725 $870
14,507
kWh
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,329 $3,039 $3,329
55,489
kWh
- - -
TOTAL RECOMMENDED $53,883 $21,182 $33,492
558,200
kWh
$6,593
-
kW-mo/yr
$(-778.5)
-
MMBtu
$14,576
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs