Assessment Year | 2010 |
---|---|
Principal Product | Needle Roller Bearings |
NAICS | 332991: Ball and Roller Bearing Manufacturing |
SIC | 3562: Ball and Roller Bearings |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
267,000
ft2
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $584,872 | 21,661,909 |
kWh
|
$0.027 |
Electricity Demand | $636,225 | 42,415 |
kW-mo/yr
|
$15.00 |
Electricity Fees | $39,237 | - |
|
- |
Natural Gas | $378,618 | 67,440 |
MMBtu
|
$5.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $511,106 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,036 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,133 | $1,250 |
$643
23,827
kWh
|
$490
-
kW-mo/yr
|
- | |
02 | 2.4314: Use synthetic lubricant | $1,632 | - |
$926
34,302
kWh
|
$706
-
kW-mo/yr
|
- | |
03 | 2.2515: Use optimum thickness insulation | $53,185 | $6,187 |
$53,185
1,969,782
kWh
|
- | - | |
04 | 2.3191: Use demand controller or load shedder | $6,159 | $2,883 |
$6,159
228,125
kWh
|
- | - | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $19,038 | $20,250 |
$19,038
705,120
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,115 | $38,366 |
$4,576
169,481
kWh
|
$5,539
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,744 | $119,989 |
$12,552
464,875
kWh
|
$15,192
-
kW-mo/yr
|
- | |
08 | 2.7273: Install desiccant humidity control system | $392,100 | $177,900 |
$71,880
2,662,143
kWh
|
$61,720
-
kW-mo/yr
|
$258,500
-
MMBtu
|
|
TOTAL RECOMMENDED | $511,106 | $366,825 |
$168,959
6,257,655
kWh
|
$83,647
-
kW-mo/yr
|
$258,500
-
MMBtu
|
||
TOTAL IMPLEMENTED | $35,036 | $124,122 |
$19,354
716,827
kWh
|
$15,682
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs