| Assessment Year | 2022 |
|---|---|
| Principal Product | Cable, Wire Harness, Precision Machining |
| NAICS | 332721: Precision Turned Product Manufacturing |
| SIC | 3451: Screw Machine Products |
| Sales Range | $1 M to 5M |
| # of Employees | 31 |
| Plant Area |
50,000
ft2
|
| Annual Production | 300,000
pieces
|
| Production Hrs. Annual | 4,810
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $54,294 | 680,640 |
kWh
|
$0.080 | |
| Electricity Demand | $28,437 | 2,152 |
kW-mo/yr
|
$13.21 | |
| Electricity Fees | $8,819 | - |
|
- | |
| Natural Gas | $11,277 | 1,694 |
MMBtu
|
$6.66 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,000 | 150 |
Tgal
|
$6.67 | |
| TOTAL YEARLY COSTS | $103,827 | ||||
| RECOMMENDED SAVINGS* | $18,471 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $1,266 | - |
$1,266
15,828
kWh
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,837 | $2,064 |
$8,943
111,784
kWh
|
$3,685
-
kW-mo/yr
|
- | $209 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,106 | $875 |
$2,106
26,329
kWh
|
- | - | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,422 | $650 | - |
$1,422
-
kW-mo/yr
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $525 | $462 |
$525
6,567
kWh
|
- | - | - | |
| 06 | 2.7314: Reduce ventilation air | $314 | $510 |
$114
1,422
kWh
|
- |
$200
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $18,471 | $4,561 |
$12,954
161,930
kWh
|
$5,107
-
kW-mo/yr
|
$200
-
MMBtu
|
$209 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs