ITAC Assessment: SU0520
ITAC logo
ITAC Assessment: SU0520
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Steel Fabrication
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 64
Plant Area 122,186
ft2
Annual Production 100,000
units
Production Hrs. Annual 7,300
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,912 1,608,956
kWh
Electricity Demand $64,451 5,647
kW-mo/yr
Electricity Fees $13,172 -
Natural Gas $55,824 11,587
MMBtu
TOTAL YEARLY COSTS $193,358
RECOMMENDED SAVINGS* $166,537 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4314: Use synthetic lubricant $540 - $226
6,092
kWh
$315
-
kW-mo/yr
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,448 $758 - $6,448
-
kW-mo/yr
- -
03 2.1321: Replace fossil fuel equipment with electrical equipment $147,518 $63,000 $(-7,108.9)
(-191,100)
kWh
- - $154,627
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,573 $5,527 $4,890
131,450
kWh
$2,466
-
kW-mo/yr
- $217
05 2.7447: Install vinyl strip / high speed / air curtain doors $3,727 $4,920 $(-68.8)
(-1,850)
kWh
- $3,796
-
MMBtu
-
06 2.7314: Reduce ventilation air $557 $882 $227
6,114
kWh
- $329
-
MMBtu
-
07 2.4239: Eliminate or reduce compressed air usage $173 $831 $173
4,677
kWh
- - -
TOTAL RECOMMENDED $166,537 $75,917 $(-1,661.8)
(-44,617)
kWh
$9,229
-
kW-mo/yr
$4,125
-
MMBtu
$154,845
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs