Assessment Year | 2009 |
---|---|
Principal Product | Plywood |
NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
1,000,000
ft2
|
Annual Production | 150,000
thousand feet
|
Production Hrs. Annual | 7,448
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,836,527 | 48,920,000 |
kWh
|
$0.038 |
Electricity Demand | $389,319 | 104,272 |
kW-mo/yr
|
$3.73 |
Natural Gas | $28,421 | 1,025 |
MMBtu
|
$27.73 |
Wood | $1,500,000 | 900,000 |
MMBtu
|
$1.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $407,023 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,631 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6126: Keep solid fuels / raw materials dry | $294,300 | $290,000 | - | - |
$294,300
-
MMBtu
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $47,605 | $128,300 |
$38,182
979,274
kWh
|
$9,423
-
kW-mo/yr
|
- | - | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $21,000 | $8,800 |
$21,000
540,220
kWh
|
- | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $15,295 | - |
$12,502
320,653
kWh
|
$2,793
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,882 | $9,900 |
$8,684
222,724
kWh
|
$1,198
-
kW-mo/yr
|
- | - | |
06 | 2.7131: Add area lighting switches | $8,092 | $1,600 |
$5,592
143,430
kWh
|
- | - | $2,500 | |
07 | 2.4224: Upgrade controls on compressors | $7,349 | - |
$7,349
188,479
kWh
|
- | - | - | |
08 | 2.2136: Install / repair insulation on steam lines | $3,500 | $600 | - | - |
$3,500
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $407,023 | $439,200 |
$93,309
2,394,780
kWh
|
$13,414
-
kW-mo/yr
|
$297,800
-
MMBtu
|
$2,500 | ||
TOTAL IMPLEMENTED | $83,631 | $138,800 |
$66,717
1,711,130
kWh
|
$13,414
-
kW-mo/yr
|
$3,500
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs