Assessment Year | 2022 |
---|---|
Principal Product | Electro-plating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 37 |
Plant Area |
29,000
ft2
|
Annual Production | 70,000
pieces
|
Production Hrs. Annual | 6,205
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $46,066 | 1,016,853 |
kWh
|
$0.045 | |
Electricity Demand | $16,970 | 1,340 |
kW-mo/yr
|
$12.66 | |
Electricity Fees | $7,711 | - |
|
- | |
Natural Gas | $23,227 | 4,677 |
MMBtu
|
$4.97 | |
Waste Disposal Costs | |||||
Water Usage | $11,200 | 1,200 |
Tgal
|
$9.33 | |
TOTAL YEARLY COSTS | $105,174 | ||||
RECOMMENDED SAVINGS* | $8,599 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $6,652 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $439 | - |
$439
9,753
kWh
|
- | - | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $1,098 | $31 |
$819
18,200
kWh
|
$665
-
kW-mo/yr
|
$(-385.8)
-
MMBtu
|
- | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $1,957 | $290 |
$(-20.0)
(-445)
kWh
|
$(-16.3)
-
kW-mo/yr
|
$1,993
-
MMBtu
|
- | |
04 | 2.8121: Apply for tax-free status for energy purchases | $858 | $160 | - | - | - | $858 | |
05 | 2.4221: Install compressor air intakes in coolest locations | $541 | $252 |
$541
12,032
kWh
|
- | - | - | |
06 | 2.2136: Install / repair insulation on steam lines | $336 | $194 | - | - |
$336
-
MMBtu
|
- | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $857 | $696 | - |
$857
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,406 | $1,750 |
$1,406
31,247
kWh
|
- | - | - | |
09 | 2.7314: Reduce ventilation air | $1,107 | $2,030 |
$216
4,793
kWh
|
- |
$891
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $8,599 | $5,403 |
$3,401
75,580
kWh
|
$1,505
-
kW-mo/yr
|
$2,835
-
MMBtu
|
$858 | ||
TOTAL IMPLEMENTED | $6,652 | $3,401 |
$1,454
32,301
kWh
|
$1,505
-
kW-mo/yr
|
$2,835
-
MMBtu
|
$858 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs