ITAC Assessment: TN0689
ITAC logo
ITAC Assessment: TN0689
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product dry-type transformers
NAICS
n/a
SIC 3612: Power, Distribution, and Specialty Transformers
Sales Range $10
M
to 50
M
# of Employees 252
Plant Area 150,000
ft2
Annual Production 62,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,448 2,252,052
kWh
Electricity Demand $33,457 7,684
kW-mo/yr
Natural Gas $124,433 25,526
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $169,505 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $112,215

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Product Savings
01 4.721: Initiate a program to acquire iso certification $97,005 $100,000 $6,470
184,349
kWh
- - $535
-
lb
- - $90,000
02 3.1161: Eliminate/reduce an operation $35,890 $108,460 - - $31,880
-
MMBtu
- $4,010
-
lb
- -
03 2.3191: Use demand controller or load shedder $8,180 $18,900 - $8,180
-
kW-mo/yr
- - - - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $7,245 $5,625 - - - $1,255
-
lb
- $5,990 -
05 2.2437: Recover waste heat from equipment $6,460 $19,500 $6,460
386,284
kWh
- - - - - -
06 2.8113: Purchase gas directly from a contract gas supplier $6,220 - - - - - - $6,220 -
07 3.8124: Install floating covers on tanks of volatile materials to reduce evaporation $4,345 $300 - - - - $4,345
-
lb
- -
08 2.7131: Add area lighting switches $3,620 $6,160 $3,620
77,960
kWh
- - - - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $540 - $310
11,430
kWh
$230
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $169,505 $258,945 $16,860
660,023
kWh
$8,410
-
kW-mo/yr
$31,880
-
MMBtu
$1,790
-
lb
$8,355
-
lb
$12,210 $90,000
TOTAL IMPLEMENTED $112,215 $112,085 $10,090
262,309
kWh
- - $1,790
-
lb
$4,345
-
lb
$5,990 $90,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs