ITAC Assessment: SU0495
ITAC logo
ITAC Assessment: SU0495
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Sheet Metal
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 121
Plant Area 151,100
ft2
Annual Production 988,000
units
Production Hrs. Annual 5,648
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $183,933 4,162,583
kWh
Electricity Demand $194,858 53,881
kW-mo/yr
Electricity Fees $23,100 -
Natural Gas $88,750 15,903
MMBtu
TOTAL YEARLY COSTS $490,641
RECOMMENDED SAVINGS* $25,660 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $703 $55 $739
16,800
kWh
$380
-
kW-mo/yr
$(-416.0)
-
MMBtu
- -
02 2.7314: Reduce ventilation air $2,795 $917 $958
21,767
kWh
- $1,837
-
MMBtu
- -
03 2.7135: Install occupancy sensors $756 $547 $756
17,186
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $424 $436 $212
4,818
kWh
$24
-
kW-mo/yr
- $77 $111
05 2.4221: Install compressor air intakes in coolest locations $765 $1,343 $765
17,393
kWh
- - - -
06 3.1161: Eliminate/reduce an operation $4,106 $7,548 $(-34.0)
(-766)
kWh
$(-369.0)
-
kW-mo/yr
- $1,936 $2,573
07 2.7142: Utilize higher efficiency lamps and/or ballasts $16,111 $36,548 $14,311
325,257
kWh
$4,344
-
kW-mo/yr
- $1,012 $(-3,556.0)
TOTAL RECOMMENDED $25,660 $47,394 $17,707
402,455
kWh
$4,379
-
kW-mo/yr
$1,421
-
MMBtu
$3,025 $(-872.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs