| Assessment Year | 2019 |
|---|---|
| Principal Product | MEMs Accelerometers |
| NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
| SIC | 3676: Electronic Resistors |
| Sales Range | $10 M to 50M |
| # of Employees | 84 |
| Plant Area |
68,200
ft2
|
| Annual Production | 100
units
|
| Production Hrs. Annual | 4,368
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $339,275 | 7,470,933 |
kWh
|
$0.045 |
| Electricity Demand | $138,775 | 12,724 |
kW-mo/yr
|
$10.91 |
| Electricity Fees | $6,135 | - |
|
- |
| Natural Gas | $25,245 | 3,573 |
MMBtu
|
$7.07 |
| TOTAL YEARLY COSTS | $509,430 | |||
| RECOMMENDED SAVINGS* | $26,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,278 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,583 | - |
$1,583
34,869
kWh
|
- | - | - | - | |
| 02 | 2.7314: Reduce ventilation air | $11,708 | $882 |
$1,942
42,788
kWh
|
- |
$9,766
-
MMBtu
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,512 | $1,311 |
$1,512
33,591
kWh
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $922 | $899 |
$406
8,935
kWh
|
$134
-
kW-mo/yr
|
- | $182 | $201 | |
| 05 | 2.7135: Install occupancy sensors | $1,917 | $2,919 |
$1,917
42,241
kWh
|
- | - | - | - | |
| 06 | 2.6211: Conserve energy by efficient use of vending machines | $109 | $200 |
$109
2,411
kWh
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,439 | $20,587 |
$4,944
108,906
kWh
|
$3,077
-
kW-mo/yr
|
- | $558 | $(-140.0) | |
| TOTAL RECOMMENDED | $26,190 | $26,798 |
$12,413
273,741
kWh
|
$3,211
-
kW-mo/yr
|
$9,766
-
MMBtu
|
$740 | $61 | ||
| TOTAL IMPLEMENTED | $11,278 | $24,405 |
$7,267
160,082
kWh
|
$3,211
-
kW-mo/yr
|
- | $740 | $61 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs