ITAC Assessment: SU0468
ITAC logo
ITAC Assessment: SU0468
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Fluid Milk
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 50,000
ft2
Annual Production 300,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $165,825 3,691,820
kWh
Electricity Demand $92,820 8,889
kW-mo/yr
Electricity Fees $19,827 -
Natural Gas $353,049 85,739
MMBtu
Waste Disposal Costs
Water Usage $102,000 1,800,000
Tgal
TOTAL YEARLY COSTS $733,521
RECOMMENDED SAVINGS* $29,352 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $1,204 $316 $1,204
26,765
kWh
- - -
02 2.2511: Insulate bare equipment $2,578 $1,066 - - $2,578
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,945 $3,308 $4,439
98,641
kWh
$1,441
-
kW-mo/yr
- $65
04 2.2123: Insulate feedwater tank $205 $136 - - $205
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $266 $260 $118
2,628
kWh
$38
-
kW-mo/yr
- $110
06 2.7135: Install occupancy sensors $2,378 $3,342 $2,378
52,842
kWh
- - -
07 2.4133: Use most efficient type of electric motors $16,776 $58,680 $16,776
372,800
kWh
- - -
TOTAL RECOMMENDED $29,352 $67,108 $24,915
553,676
kWh
$1,479
-
kW-mo/yr
$2,783
-
MMBtu
$175
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs