Assessment Year | 2018 |
---|---|
Principal Product | Zirconias and Titanates |
NAICS | 327992: Ground or Treated Mineral and Earth Manufacturing |
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
330,000
ft2
|
Annual Production | 4,800,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $467,974 | 33,970,723 |
kWh
|
$0.014 | |
Electricity Demand | $647,012 | 58,589 |
kW-mo/yr
|
$11.04 | |
Electricity Fees | $65,060 | - |
|
- | |
Natural Gas | $148,137 | 34,110 |
MMBtu
|
$4.34 | |
Waste Disposal Costs | |||||
Water Usage | $49,140 | 16,494,503 |
Tgal
|
$0.003 | |
TOTAL YEARLY COSTS | $1,377,323 | ||||
RECOMMENDED SAVINGS* | $69,202 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,966 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $3,799 | $2,040 |
$3,799
275,309
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,444 | $22,334 |
$6,990
506,539
kWh
|
$19,744
-
kW-mo/yr
|
- | $1,573 | $(-863.0) | |
03 | 2.4322: Use or replace with energy efficient substitutes | $29,334 | $68,970 |
$13,834
1,002,456
kWh
|
$15,500
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,966 | $4,800 |
$1,966
140,402
kWh
|
- | - | - | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $3,314 | $8,600 | - | - |
$3,314
-
MMBtu
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,345 | $14,020 |
$3,345
242,428
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $69,202 | $120,764 |
$29,934
2,167,134
kWh
|
$35,244
-
kW-mo/yr
|
$3,314
-
MMBtu
|
$1,573 | $(-863.0) | ||
TOTAL IMPLEMENTED | $1,966 | $4,800 |
$1,966
140,402
kWh
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs