ITAC Assessment: SU0463
ITAC logo
ITAC Assessment: SU0463
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Zirconias and Titanates
NAICS 327992: Ground or Treated Mineral and Earth Manufacturing
SIC 3295: Minerals and Earths, Ground or Otherwise Treated
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 330,000
ft2
Annual Production 4,800,000
units
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $467,974 33,970,723
kWh
Electricity Demand $647,012 58,589
kW-mo/yr
Electricity Fees $65,060 -
Natural Gas $148,137 34,110
MMBtu
Waste Disposal Costs
Water Usage $49,140 16,494,503
Tgal
TOTAL YEARLY COSTS $1,377,323
RECOMMENDED SAVINGS* $69,202 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,966

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7135: Install occupancy sensors $3,799 $2,040 $3,799
275,309
kWh
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $27,444 $22,334 $6,990
506,539
kWh
$19,744
-
kW-mo/yr
- $1,573 $(-863.0)
03 2.4322: Use or replace with energy efficient substitutes $29,334 $68,970 $13,834
1,002,456
kWh
$15,500
-
kW-mo/yr
- - -
04 2.4221: Install compressor air intakes in coolest locations $1,966 $4,800 $1,966
140,402
kWh
- - - -
05 2.2414: Use waste heat from hot flue gases to preheat $3,314 $8,600 - - $3,314
-
MMBtu
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,345 $14,020 $3,345
242,428
kWh
- - - -
TOTAL RECOMMENDED $69,202 $120,764 $29,934
2,167,134
kWh
$35,244
-
kW-mo/yr
$3,314
-
MMBtu
$1,573 $(-863.0)
TOTAL IMPLEMENTED $1,966 $4,800 $1,966
140,402
kWh
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs