| Assessment Year | 2018 |
|---|---|
| Principal Product | Wheat Flour |
| NAICS | 311211: Flour Milling |
| SIC | 2041: Flour and Other Grain Mill Products |
| Sales Range | $100 M to 500M |
| # of Employees | 80 |
| Plant Area |
400,000
ft2
|
| Annual Production | 540,000,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $622,408 | 26,269,300 |
kWh
|
$0.024 |
| Electricity Demand | $572,242 | 60,021 |
kW-mo/yr
|
$9.53 |
| Electricity Fees | $34,753 | - |
|
- |
| Natural Gas | $59,941 | 13,066 |
MMBtu
|
$4.59 |
| TOTAL YEARLY COSTS | $1,289,344 | |||
| RECOMMENDED SAVINGS* | $76,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $76,760 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $6,138 | - | - | - | - | - | - | $6,138 | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $717 | - |
$717
29,857
kWh
|
- | - | - | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $150 | - | - | - | - |
$150
-
MMBtu
|
- | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $28,600 | $675 | - |
$28,600
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 3.1161: Eliminate/reduce an operation | $5,417 | $1,800 |
$(-22.0)
(-910)
kWh
|
$(-229.0)
-
kW-mo/yr
|
- | - | $1,300 | $4,368 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $194 | $125 |
$32
1,314
kWh
|
$17
-
kW-mo/yr
|
- | - | $84 | $61 | |
| 07 | 2.3212: Optimize plant power factor | $27,797 | $38,674 | - | - | $27,797 | - | - | - | |
| 08 | 2.7135: Install occupancy sensors | $6,863 | $15,312 |
$6,863
285,966
kWh
|
- | - | - | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $884 | $2,658 |
$799
33,288
kWh
|
$440
-
kW-mo/yr
|
- | - | $17 | $(-372.0) | |
| TOTAL RECOMMENDED | $76,760 | $59,244 |
$8,389
349,515
kWh
|
$28,828
-
kW-mo/yr
|
$27,797 |
$150
-
MMBtu
|
$1,401 | $10,195 | ||
| TOTAL IMPLEMENTED | $76,760 | $59,244 |
$8,389
349,515
kWh
|
$28,828
-
kW-mo/yr
|
$27,797 |
$150
-
MMBtu
|
$1,401 | $10,195 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs