ITAC Assessment: SU0446
ITAC logo
ITAC Assessment: SU0446
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Workstation and Jib Cranes
NAICS 333923: Overhead Traveling Crane, Hoist, and Monorail System Manufacturing
SIC 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 119,500
ft2
Annual Production 7,500
units
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $64,028 1,209,437
kWh
Electricity Demand $96,503 6,866
kW-mo/yr
Electricity Fees $8,680 -
Natural Gas $62,198 10,459
MMBtu
Waste Disposal Costs
Water Usage $895 217
Tgal
TOTAL YEARLY COSTS $232,304
RECOMMENDED SAVINGS* $19,529 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,929

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.6218: Turn off equipment when not in use $1,759 - $1,759
33,187
kWh
- - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $10,711 $7,161 $17,363
327,600
kWh
- $(-6,652.0)
-
MMBtu
- -
03 2.4221: Install compressor air intakes in coolest locations $304 $234 $304
5,739
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $170 $165 $88
1,664
kWh
$32
-
kW-mo/yr
- $30 $20
05 2.2314: Replace heat treating oven with more efficient unit $6,295 $18,204 - - $6,295
-
MMBtu
- -
06 2.6211: Conserve energy by efficient use of vending machines $290 $854 $290
5,474
kWh
- - - -
TOTAL RECOMMENDED $19,529 $26,618 $19,804
373,664
kWh
$32
-
kW-mo/yr
$(-357.0)
-
MMBtu
$30 $20
TOTAL IMPLEMENTED $1,929 $165 $1,847
34,851
kWh
$32
-
kW-mo/yr
- $30 $20
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs