| Assessment Year | 2016 |
|---|---|
| Principal Product | Fabricated Structural Metal Manufacturing |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 24 |
| Plant Area |
52,000
ft2
|
| Annual Production | 33,500,000
pieces
|
| Production Hrs. Annual | 2,168
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $15,152 | 354,700 |
kWh
|
$0.043 |
| Electricity Demand | $20,183 | 1,947 |
kW-mo/yr
|
$10.37 |
| Electricity Fees | $4,385 | - |
|
- |
| Natural Gas | $2,876 | 441 |
MMBtu
|
$6.52 |
| TOTAL YEARLY COSTS | $42,596 | |||
| RECOMMENDED SAVINGS* | $10,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,942 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $320 | - |
$320
7,444
kWh
|
- | - | - | - | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,534 | $429 |
$1,534
35,671
kWh
|
- | - | - | - | |
| 03 | 3.1161: Eliminate/reduce an operation | $2,385 | $5,280 |
$(-32.0)
(-750)
kWh
|
$(-373.0)
-
kW-mo/yr
|
- | $1,190 | $1,600 | |
| 04 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $969 | $2,348 | - | - |
$969
-
MMBtu
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $124 | $418 |
$124
2,879
kWh
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,930 | $18,947 |
$2,020
46,981
kWh
|
$2,696
-
kW-mo/yr
|
- | $694 | $(-480.6) | |
| TOTAL RECOMMENDED | $10,262 | $27,422 |
$3,966
92,225
kWh
|
$2,323
-
kW-mo/yr
|
$969
-
MMBtu
|
$1,884 | $1,119 | ||
| TOTAL IMPLEMENTED | $9,942 | $27,422 |
$3,646
84,781
kWh
|
$2,323
-
kW-mo/yr
|
$969
-
MMBtu
|
$1,884 | $1,119 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs