Assessment Year | 2015 |
---|---|
Principal Product | Packaging Machinery |
NAICS | 333993: Packaging Machinery Manufacturing |
SIC | 3565: Packaging Machinery |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
86,577
ft2
|
Annual Production | 38
pieces
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,843 | 954,925 |
kWh
|
$0.051 |
Electricity Demand | $45,249 | 3,746 |
kW-mo/yr
|
$12.08 |
Electricity Fees | $1,110 | - |
|
- |
Natural Gas | $9,322 | 1,611 |
MMBtu
|
$5.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,688 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,821 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $1,256 | - | - | - | $1,256 | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $130 | - |
$72
1,412
kWh
|
$58
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $867 | $868 |
$867
16,995
kWh
|
- | - | - | |
04 | 3.1161: Eliminate/reduce an operation | $4,385 | $5,848 |
$(-624.0)
(-12,240)
kWh
|
$(-870.0)
-
kW-mo/yr
|
- | $5,879 | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $37 | $110 |
$37
724
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13 | $55 |
$6
125
kWh
|
$7
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $6,688 | $6,881 |
$358
7,016
kWh
|
$(-805.0)
-
kW-mo/yr
|
$1,256 | $5,879 | ||
TOTAL IMPLEMENTED | $5,821 | $6,013 |
$(-509.0)
(-9,979)
kWh
|
$(-805.0)
-
kW-mo/yr
|
$1,256 | $5,879 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs