| Assessment Year | 2015 |
|---|---|
| Principal Product | Super Alloy Metals |
| NAICS | 331492: Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum) |
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 125 |
| Plant Area |
130,000
ft2
|
| Annual Production | 2,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $283,209 | 5,604,337 |
kWh
|
$0.051 |
| Electricity Demand | $80,997 | 23,525 |
kW-mo/yr
|
$3.44 |
| Natural Gas | $49,113 | 6,458 |
MMBtu
|
$7.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,297,002 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,487 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Gaseous Waste Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $854 | $514 |
$210
4,118
kWh
|
$19
-
kW-mo/yr
|
- | - | $475 | $150 | |
| 02 | 3.5311: Recover and reuse waste material | $1,281,641 | $1,000,000 |
$(-134,028.0)
(-2,628,000)
kWh
|
$(-12,384.0)
-
kW-mo/yr
|
- |
$1,428,053
-
lb
|
- | - | |
| 03 | 3.1161: Eliminate/reduce an operation | $4,112 | $3,576 |
$(-99.0)
(-1,950)
kWh
|
$(-124.0)
-
kW-mo/yr
|
- | - | $1,900 | $2,435 | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,129 | $998 |
$1,129
22,147
kWh
|
- | - | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,883 | $2,400 |
$1,883
36,912
kWh
|
- | - | - | - | - | |
| 06 | 2.3212: Optimize plant power factor | $5,745 | $12,259 | - | - | $5,745 | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,638 | $5,256 |
$1,050
20,586
kWh
|
$194
-
kW-mo/yr
|
- | - | $114 | $280 | |
| TOTAL RECOMMENDED | $1,297,002 | $1,025,003 |
$(-129,855.0)
(-2,546,187)
kWh
|
$(-12,295.0)
-
kW-mo/yr
|
$5,745 |
$1,428,053
-
lb
|
$2,489 | $2,865 | ||
| TOTAL IMPLEMENTED | $8,487 | $11,746 |
$3,044
59,666
kWh
|
$89
-
kW-mo/yr
|
- | - | $2,489 | $2,865 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Gaseous Waste Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs