ITAC Assessment: SU0360
ITAC logo
ITAC Assessment: SU0360
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Plastic Consumer Product
NAICS 326140: Polystyrene Foam Product Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $1
M
to 5
M
# of Employees 700
Plant Area 500,000
ft2
Annual Production 25,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $6,412,981 90,196,953
kWh
Electricity Demand $1,575,510 191,452
kW-mo/yr
Natural Gas $252,420 46,157
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,001 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,264

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $14,245 $685 $14,245
200,350
kWh
- - -
02 2.2437: Recover waste heat from equipment $4,540 $685 - - - $4,540
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,074 $3,375 $16,074
226,400
kWh
- - -
04 2.6211: Conserve energy by efficient use of vending machines $1,863 $3,874 $1,863
26,208
kWh
- - -
05 2.4321: Upgrade obsolete equipment $1,190 $3,188 $1,027
14,454
kWh
$163
-
kW-mo/yr
- -
06 2.3212: Optimize plant power factor $28,089 $129,616 - - $28,089 -
TOTAL RECOMMENDED $66,001 $141,423 $33,209
467,412
kWh
$163
-
kW-mo/yr
$28,089 $4,540
-
MMBtu
TOTAL IMPLEMENTED $17,264 $6,563 $17,101
240,854
kWh
$163
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs