| Assessment Year | 2013 |
|---|---|
| Principal Product | Corrugated Paper Products |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $100 M to 500M |
| # of Employees | 70 |
| Plant Area |
193,635
ft2
|
| Annual Production | 2,101,541
thousand feet
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $65,097 | 4,561,552 |
kWh
|
$0.014 |
| Electricity Demand | $56,541 | 9,076 |
kW-mo/yr
|
$6.23 |
| Electricity Fees | $117,188 | - |
|
- |
| Natural Gas | $327,871 | 87,702 |
MMBtu
|
$3.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,097 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,844 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $837 | - |
$451
32,198
kWh
|
$386
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $263 | - |
$76
5,400
kWh
|
$187
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $1,638 | $267 | - | - | - |
$1,638
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $628 | $290 |
$61
4,353
kWh
|
$37
-
kW-mo/yr
|
- | - | $530 | |
| 05 | 2.7135: Install occupancy sensors | $743 | $498 |
$743
53,053
kWh
|
- | - | - | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $1,473 | $1,292 | - | - | - |
$1,473
-
MMBtu
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $281 | $240 |
$281
20,095
kWh
|
- | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $384 | $504 |
$118
8,424
kWh
|
$106
-
kW-mo/yr
|
- | - | $160 | |
| 09 | 3.1161: Eliminate/reduce an operation | $1,693 | $3,338 |
$(-8.0)
(-555)
kWh
|
$(-336.0)
-
kW-mo/yr
|
- | - | $2,037 | |
| 10 | 2.3212: Optimize plant power factor | $5,157 | $14,874 | - | - | $5,157 | - | - | |
| TOTAL RECOMMENDED | $13,097 | $21,303 |
$1,722
122,968
kWh
|
$380
-
kW-mo/yr
|
$5,157 |
$3,111
-
MMBtu
|
$2,727 | ||
| TOTAL IMPLEMENTED | $2,844 | $2,080 |
$804
57,406
kWh
|
$37
-
kW-mo/yr
|
- |
$1,473
-
MMBtu
|
$530 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs