ITAC Assessment: SD0161
ITAC logo
ITAC Assessment: SD0161
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Thermo Plastic Injected Molded parts
NAICS
n/a
SIC 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 100,000
ft2
Annual Production 20,400,000
pieces
Production Hrs. Annual 7,650
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $433,081 7,647,714
kWh
Electricity Demand $144,641 15,205
kW-mo/yr
Natural Gas $723 67
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $220,421 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $144,945

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $24,903 $21,360 $19,485
342,028
kWh
$5,418
-
kW-mo/yr
- - - -
02 2.1224: Replace boiler $38,307 $8,000 $88,284
1,549,238
kWh
$20,456
-
kW-mo/yr
$(-70,433.0)
-
MMBtu
- - -
03 2.6212: Turn off equipment during breaks, reduce operating time $14,372 - $11,245
197,245
kWh
$3,127
-
kW-mo/yr
- - - -
04 2.4226: Use / purchase optimum sized compressor $4,046 $4,000 $2,696
47,186
kWh
$1,350
-
kW-mo/yr
- - - -
05 2.2515: Use optimum thickness insulation $3,460 $108 $3,460
60,668
kWh
- - - - -
06 2.2628: Utilize a less expensive cooling method $2,460 $900 $2,460
43,083
kWh
- - - - -
07 4.652: Replace existing equipment with more suitable substitutes $1,573 $1,800 - - - - $1,573 -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $965 $2,700 $755
13,189
kWh
$210
-
kW-mo/yr
- - - -
09 2.7144: Install spectral reflectors / delamp $8,614 $10,360 $5,913
103,751
kWh
$2,701
-
kW-mo/yr
- - - -
10 2.7135: Install occupancy sensors $1,963 $820 $1,341
23,447
kWh
$622
-
kW-mo/yr
- - - -
11 3.8132: Use less toxic and volatile solvent substitutes $496 - - - - $496
-
gal
- -
12 3.6193: Install equipment (eg compactor) to reduce disposal costs $14,696 $9,000 - - - - - $14,696
13 4.321: Optimize production lot sizes and inventories $33,136 $8,000 - - - - - $33,136
14 4.521: Clear and rent existing space $23,046 $152 - - - - - $23,046
15 4.512: Condense operation into one building $48,384 - - - - - - $48,384
TOTAL RECOMMENDED $220,421 $67,200 $135,639
2,379,835
kWh
$33,884
-
kW-mo/yr
$(-70,433.0)
-
MMBtu
$496
-
gal
$1,573 $119,262
TOTAL IMPLEMENTED $144,945 $48,500 $44,895
787,514
kWh
$13,428
-
kW-mo/yr
- $496
-
gal
- $86,126
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs