ITAC Assessment: SU0342
ITAC logo
ITAC Assessment: SU0342
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Screw Machine Products
NAICS 332721: Precision Turned Product Manufacturing
SIC 3451: Screw Machine Products
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 140,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $181,419 3,305,565
kWh
Electricity Demand $33,869 3,165
kW-mo/yr
Electricity Fees $25,487 -
Natural Gas $18,882 2,677
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,379 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $344

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $1,615 $620 $1,615
40,366
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $209 $92 $48
1,205
kWh
$18
-
kW-mo/yr
$99 $44
03 2.6211: Conserve energy by efficient use of vending machines $211 $914 $211
5,285
kWh
- - -
04 2.4321: Upgrade obsolete equipment $344 $1,388 $250
6,247
kWh
$94
-
kW-mo/yr
- -
TOTAL RECOMMENDED $2,379 $3,014 $2,124
53,103
kWh
$112
-
kW-mo/yr
$99 $44
TOTAL IMPLEMENTED $344 $1,388 $250
6,247
kWh
$94
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs