ITAC Assessment: SU0327
ITAC logo
ITAC Assessment: SU0327
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Diffraction Gratings
NAICS 333314: Optical Instrument and Lens Manufacturing
SIC 3827: Optical Instruments and Lenses
Sales Range $50
M
to 100
M
# of Employees 56
Plant Area 57,700
ft2
Annual Production 59,000
pieces
Production Hrs. Annual 5,100
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $441,645 6,250,183
kWh
Electricity Demand $91,213 7,773
kW-mo/yr
Electricity Fees $130,078 -
Natural Gas $18,654 5,722
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,132 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,845

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $728 - $441
7,072
kWh
$287
-
kW-mo/yr
- -
02 4.821: Pay bills on time to avoid late fees $287 - - - - $287
03 2.4221: Install compressor air intakes in coolest locations $870 $858 $870
15,855
kWh
- - -
04 2.7314: Reduce ventilation air $2,247 $4,271 $77
1,414
kWh
- $2,170
-
MMBtu
-
TOTAL RECOMMENDED $4,132 $5,129 $1,388
24,341
kWh
$287
-
kW-mo/yr
$2,170
-
MMBtu
$287
TOTAL IMPLEMENTED $3,845 $5,129 $1,388
24,341
kWh
$287
-
kW-mo/yr
$2,170
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs