| Assessment Year | 2011 |
|---|---|
| Principal Product | Nickel Cobalt based superalloy materials |
| NAICS | 331492: Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum) |
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 100 |
| Plant Area |
127,000
ft2
|
| Annual Production | 75,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $523,581 | 5,108,647 |
kWh
|
$0.10 |
| Electricity Demand | $209,273 | 28,515 |
kW-mo/yr
|
$7.34 |
| Electricity Fees | $(-54,564.0) | - |
|
- |
| Natural Gas | $69,137 | 5,423 |
MMBtu
|
$12.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,477 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3137: Use power during off-peak periods | $4,632 | - | - | - | - | $4,632 | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,978 | $689 |
$2,978
28,908
kWh
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $2,477 | $2,028 |
$2,477
24,046
kWh
|
- | - | - | |
| 04 | 3.5145: Recover and reuse spent acid baths | $1,049 | $958 |
$(-62.0)
(-600)
kWh
|
$(-9.0)
-
kW-mo/yr
|
- | $1,120 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $377 | $487 |
$180
1,752
kWh
|
$18
-
kW-mo/yr
|
- | $179 | |
| 06 | 2.6211: Conserve energy by efficient use of vending machines | $496 | $895 |
$496
4,817
kWh
|
- | - | - | |
| 07 | 3.1191: Change procedures / equipment / operating conditions | $11,025 | $26,043 |
$(-2,887.0)
(-28,032)
kWh
|
$(-279.0)
-
kW-mo/yr
|
- | $14,191 | |
| 08 | 2.3212: Optimize plant power factor | $5,328 | $18,204 | - | - | $5,328 | - | |
| TOTAL RECOMMENDED | $28,362 | $49,304 |
$3,182
30,891
kWh
|
$(-270.0)
-
kW-mo/yr
|
$5,328 | $20,122 | ||
| TOTAL IMPLEMENTED | $2,477 | $2,028 |
$2,477
24,046
kWh
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs