ITAC Assessment: SU0301
ITAC logo
ITAC Assessment: SU0301
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Nickel Cobalt based superalloy materials
NAICS 331492: Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum)
SIC 3399: Primary Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 100
Plant Area 127,000
ft2
Annual Production 75,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $523,581 5,108,647
kWh
Electricity Demand $209,273 28,515
kW-mo/yr
Electricity Fees $(-54,564.0) -
Natural Gas $69,137 5,423
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,362 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,477

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.3137: Use power during off-peak periods $4,632 - - - - $4,632
02 2.4221: Install compressor air intakes in coolest locations $2,978 $689 $2,978
28,908
kWh
- - -
03 2.7135: Install occupancy sensors $2,477 $2,028 $2,477
24,046
kWh
- - -
04 3.5145: Recover and reuse spent acid baths $1,049 $958 $(-62.0)
(-600)
kWh
$(-9.0)
-
kW-mo/yr
- $1,120
05 2.7142: Utilize higher efficiency lamps and/or ballasts $377 $487 $180
1,752
kWh
$18
-
kW-mo/yr
- $179
06 2.6211: Conserve energy by efficient use of vending machines $496 $895 $496
4,817
kWh
- - -
07 3.1191: Change procedures / equipment / operating conditions $11,025 $26,043 $(-2,887.0)
(-28,032)
kWh
$(-279.0)
-
kW-mo/yr
- $14,191
08 2.3212: Optimize plant power factor $5,328 $18,204 - - $5,328 -
TOTAL RECOMMENDED $28,362 $49,304 $3,182
30,891
kWh
$(-270.0)
-
kW-mo/yr
$5,328 $20,122
TOTAL IMPLEMENTED $2,477 $2,028 $2,477
24,046
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs