| Assessment Year | 2008 |
|---|---|
| Principal Product | Ferrite Powder |
| NAICS | 327110: Pottery, Ceramics, and Plumbing Fixture Manufacturing |
| SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
| Sales Range | $10 M to 50M |
| # of Employees | 35 |
| Plant Area |
28,700
ft2
|
| Annual Production | 65,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $592,984 | 6,090,532 |
kWh
|
$0.097 |
| Electricity Demand | $195,088 | 11,242 |
kW-mo/yr
|
$17.35 |
| Electricity Fees | $7,344 | - |
|
- |
| Natural Gas | $1,117,711 | 166,715 |
MMBtu
|
$6.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $239,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $235,815 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,597 | - |
$2,889
29,784
kWh
|
$708
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4314: Use synthetic lubricant | $3,284 | - |
$2,642
3,284
kWh
|
$642
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4112: Install soft-start to eliminate nuisance trips | $84,581 | $7,850 | - |
$84,581
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $3,737 | $128 |
$3,008
31,010
kWh
|
$729
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $631 | $44 |
$510
5,256
kWh
|
$121
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $221 | $141 |
$94
964
kWh
|
$23
-
kW-mo/yr
|
- | - | - | $104 | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,553 | $10,014 |
$5,269
54,312
kWh
|
$1,284
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.6211: Conserve energy by efficient use of vending machines | $108 | $191 |
$108
1,117
kWh
|
- | - | - | - | - | |
| 09 | 2.3212: Optimize plant power factor | $3,954 | $14,012 | - | - | $3,954 | - | - | - | |
| 10 | 3.4151: Minimize water usage | $133,075 | $550,000 | - | - | - |
$126,846
-
MMBtu
|
$6,229
-
gal
|
- | |
| TOTAL RECOMMENDED | $239,741 | $582,380 |
$14,520
125,727
kWh
|
$88,088
-
kW-mo/yr
|
$3,954 |
$126,846
-
MMBtu
|
$6,229
-
gal
|
$104 | ||
| TOTAL IMPLEMENTED | $235,815 | $582,048 |
$11,429
93,862
kWh
|
$87,357
-
kW-mo/yr
|
$3,954 |
$126,846
-
MMBtu
|
$6,229
-
gal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs