ITAC Assessment: SD0073
ITAC logo
ITAC Assessment: SD0073
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Plastic Injection
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area 16,836
ft2
Annual Production 11,000
lb
Production Hrs. Annual 6,375
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $138,605 1,291,032
kWh
Natural Gas $1,486 168
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,299 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,299

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $348 $20 $348
4,396
kWh
02 2.2511: Insulate bare equipment $593 $334 $593
5,569
kWh
03 2.7132: Install timers on light switches in little used areas $3,860 $240 $3,860
33,411
kWh
04 2.7132: Install timers on light switches in little used areas $147 $75 $147
1,172
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $305 $175 $305
1,465
kWh
06 2.3137: Use power during off-peak periods $1,046 - $1,046
-
kWh
TOTAL RECOMMENDED $6,299 $844 $6,299
46,013
kWh
TOTAL IMPLEMENTED $6,299 $844 $6,299
46,013
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs