ITAC Assessment: MI0104
ITAC logo
ITAC Assessment: MI0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Soft drink manufacturing
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 380
Plant Area 180,000
ft2
Annual Production 27,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,071,636 20,433,440
kWh
Electricity Demand $357,476 43,086
kW-mo/yr
Electricity Fees $123,349 -
Natural Gas $456,543 57,824
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $367,484 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2447: Heat water with exhaust heat $315,984 $128,000 $22,854
463,515
kWh
$293,130
-
MMBtu
-
02 2.4239: Eliminate or reduce compressed air usage $23,384 $1,300 $23,384
474,346
kWh
- -
03 2.8114: Change rate schedules or other changes in utility service $9,889 $600 - - $9,889
04 2.4221: Install compressor air intakes in coolest locations $5,821 $3,010 $5,821
118,073
kWh
- -
05 2.2628: Utilize a less expensive cooling method $8,246 $10,198 $8,246
162,151
kWh
- -
06 2.4323: Use optimum size and capacity equipment $4,160 $5,060 $4,160
84,374
kWh
- -
TOTAL RECOMMENDED $367,484 $148,168 $64,465
1,302,459
kWh
$293,130
-
MMBtu
$9,889
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs