ITAC Assessment: SU0265
ITAC logo
ITAC Assessment: SU0265
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Solder Paste
NAICS 331491: Nonferrous Metal (except Copper and Aluminum) Rolling, Drawing, and Extruding
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 149
Plant Area 43,683
ft2
Annual Production 663,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $205,554 2,363,653
kWh
Electricity Demand $64,603 6,353
kW-mo/yr
Electricity Fees $51,329 -
Natural Gas $121,539 12,024
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $222,037 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,401

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $468 - - $468
-
kW-mo/yr
- -
02 2.4314: Use synthetic lubricant $191 - $141
1,622
kWh
$50
-
kW-mo/yr
- -
03 3.1191: Change procedures / equipment / operating conditions $214,622 $23,800 $(-1,357.0)
(-15,600)
kWh
$(-498.0)
-
kW-mo/yr
- $216,477
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,615 $252 $1,183
13,603
kWh
$432
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $786 $223 $537
6,178
kWh
$249
-
kW-mo/yr
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,263 $3,368 $2,366
27,198
kWh
$897
-
kW-mo/yr
- -
07 2.6211: Conserve energy by efficient use of vending machines $171 $310 $171
1,971
kWh
- - -
08 2.3212: Optimize plant power factor $921 $4,079 - - $921 -
TOTAL RECOMMENDED $222,037 $32,032 $3,041
34,972
kWh
$1,598
-
kW-mo/yr
$921 $216,477
TOTAL IMPLEMENTED $2,401 $475 $1,720
19,781
kWh
$681
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs