Assessment Year | 2007 |
---|---|
Principal Product | Wire and Tubing Processing Machines |
NAICS | 333519: Rolling Mill and Other Metalworking Machinery Manufacturing |
SIC | 3549: Metalworking Machinery, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 46 |
Plant Area |
26,856
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,247 | 331,533 |
kWh
|
$0.12 |
Electricity Demand | $15,532 | 1,616 |
kW-mo/yr
|
$9.61 |
Electricity Fees | $4,819 | - |
|
- |
Natural Gas | $10,285 | 756 |
MMBtu
|
$13.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,537 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,279 | - |
$856
7,446
kWh
|
$423
-
kW-mo/yr
|
- | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $1,332 | - | - | - | - | $1,332 | |
03 | 2.8114: Change rate schedules or other changes in utility service | $411 | - | - | - | - | $411 | |
04 | 2.7229: Air condition only space necessary | $763 | $13 |
$600
5,214
kWh
|
$163
-
kW-mo/yr
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $290 | $38 |
$175
1,520
kWh
|
$115
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $221 | $50 |
$148
1,285
kWh
|
$73
-
kW-mo/yr
|
- | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $410 | $232 |
$275
2,387
kWh
|
$135
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $272 | $231 |
$161
1,402
kWh
|
$19
-
kW-mo/yr
|
$92 | - | |
09 | 2.6211: Conserve energy by efficient use of vending machines | $508 | $546 |
$508
4,418
kWh
|
- | - | - | |
10 | 2.7135: Install occupancy sensors | $302 | $973 |
$302
2,627
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $5,788 | $2,083 |
$3,025
26,299
kWh
|
$928
-
kW-mo/yr
|
$92 | $1,743 | ||
TOTAL IMPLEMENTED | $3,537 | $1,537 |
$2,517
21,881
kWh
|
$928
-
kW-mo/yr
|
$92 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs