Assessment Year | 2007 |
---|---|
Principal Product | Lightweight Specialty Paper |
NAICS | 322121: Paper (except Newsprint) Mills |
SIC | 2621: Paper Mills |
Sales Range | $10 M to 50M |
# of Employees | 68 |
Plant Area |
135,000
ft2
|
Annual Production | 70,000,000
lb
|
Production Hrs. Annual | 8,769
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,268,484 | 34,258,817 |
kWh
|
$0.095 |
Electricity Demand | $421,545 | 61,924 |
kW-mo/yr
|
$6.81 |
Electricity Fees | $34,685 | - |
|
- |
Natural Gas | $3,011,852 | 24,706 |
MMBtu
|
$121.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $517,639 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $502,565 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $17,366 | - |
$15,753
165,816
kWh
|
$1,613
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,043 | - |
$7,505
79,002
kWh
|
$1,538
-
kW-mo/yr
|
- | - | - | |
03 | 2.4314: Use synthetic lubricant | $4,349 | - |
$3,893
40,984
kWh
|
$456
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,124 | $1,000 |
$11,906
125,328
kWh
|
$1,218
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $5,261 | $712 |
$4,369
45,990
kWh
|
$892
-
kW-mo/yr
|
- | - | - | |
06 | 2.2442: Preheat combustion air with waste heat | $323,145 | $79,171 | - | - | - |
$323,145
-
MMBtu
|
- | |
07 | 2.7135: Install occupancy sensors | $6,815 | $1,735 |
$6,815
71,736
kWh
|
- | - | - | - | |
08 | 2.2136: Install / repair insulation on steam lines | $561 | $250 | - | - | - |
$561
-
MMBtu
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $901 | $632 |
$383
4,030
kWh
|
$41
-
kW-mo/yr
|
- | - | $477 | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,859 | $12,203 |
$8,933
93,996
kWh
|
$926
-
kW-mo/yr
|
- | - | - | |
11 | 2.4321: Upgrade obsolete equipment | $112,898 | $150,000 |
$102,415
1,078,056
kWh
|
$10,483
-
kW-mo/yr
|
- | - | - | |
12 | 2.6211: Conserve energy by efficient use of vending machines | $144 | $272 |
$144
1,516
kWh
|
- | - | - | - | |
13 | 2.3212: Optimize plant power factor | $14,173 | $42,224 | - | - | $14,173 | - | - | |
TOTAL RECOMMENDED | $517,639 | $288,199 |
$162,116
1,706,454
kWh
|
$17,167
-
kW-mo/yr
|
$14,173 |
$323,706
-
MMBtu
|
$477 | ||
TOTAL IMPLEMENTED | $502,565 | $245,343 |
$161,733
1,702,424
kWh
|
$17,126
-
kW-mo/yr
|
- |
$323,706
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs