ITAC Assessment: SU0238
ITAC logo
ITAC Assessment: SU0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Artistic Glass Objects & Stemware
NAICS 327212: Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 62,395
ft2
Annual Production 128,800
lb
Production Hrs. Annual 6,000
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,000 971,607
kWh
Natural Gas $1,061,187 107,144
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $182,647 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $159,282

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
01 2.6218: Turn off equipment when not in use $98,366 - - $98,366
-
MMBtu
- - -
02 2.6241: Reduce temperature of process equipment when on standby $55,282 - - $55,282
-
MMBtu
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $6,431 - $6,431
71,460
kWh
- - - -
04 2.4314: Use synthetic lubricant $1,534 - $1,534
17,040
kWh
- - - -
05 2.7122: Disconnect ballasts $788 - $788
8,760
kWh
- - - -
06 2.4221: Install compressor air intakes in coolest locations $3,073 $578 $3,073
34,140
kWh
- - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,210 $264 $1,210
13,440
kWh
- - - -
08 3.4111: Use closed cycle process to minimize waste water production $3,018 $1,094 - - - $3,018
-
Tgal
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $477 $730 $236
2,627
kWh
- $74 - $167
10 2.7135: Install occupancy sensors $86 $127 $86
960
kWh
- - - -
11 2.6211: Conserve energy by efficient use of vending machines $378 $684 $378
4,205
kWh
- - - -
12 2.2437: Recover waste heat from equipment $12,004 $67,500 $12,004
133,375
kWh
- - - -
TOTAL RECOMMENDED $182,647 $70,977 $25,740
286,007
kWh
$153,648
-
MMBtu
$74 $3,018
-
Tgal
$167
TOTAL IMPLEMENTED $159,282 $1,699 $5,393
59,927
kWh
$153,648
-
MMBtu
$74 - $167
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings Water Consumption Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs