ITAC Assessment: UL0234
ITAC logo
ITAC Assessment: UL0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Winches, couplings, trailer jacks
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 110,000
ft2
Annual Production 1,062,500
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,423 1,569,754
kWh
Electricity Demand $23,747 5,321
kW-mo/yr
Natural Gas $50,135 12,815
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $80,022 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $62,180

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,233 $20 $734
24,033
kWh
$499
-
kW-mo/yr
- - -
02 2.4221: Install compressor air intakes in coolest locations $480 $131 $323
10,551
kWh
$157
-
kW-mo/yr
- - -
03 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance $11,305 $800 $2,505
187,866
kWh
- - $8,800 -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $4,824 - - - $4,824
-
lb
- -
05 4.122: Develop standard procedures to improve internal yields $62,180 $300 - - - - $62,180
TOTAL RECOMMENDED $80,022 $1,251 $3,562
222,450
kWh
$656
-
kW-mo/yr
$4,824
-
lb
$8,800 $62,180
TOTAL IMPLEMENTED $62,180 $300 - - - - $62,180
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs