Assessment Year | 1999 |
---|---|
Principal Product | Winches, couplings, trailer jacks |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
110,000
ft2
|
Annual Production | 1,062,500
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,423 | 1,569,754 |
kWh
|
$0.031 |
Electricity Demand | $23,747 | 5,321 |
kW-mo/yr
|
$4.46 |
Natural Gas | $50,135 | 12,815 |
MMBtu
|
$3.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $80,022 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,180 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,233 | $20 |
$734
24,033
kWh
|
$499
-
kW-mo/yr
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $480 | $131 |
$323
10,551
kWh
|
$157
-
kW-mo/yr
|
- | - | - | |
03 | 3.2111: Install redundant equipment to avoid losses caused by equipment failure and routine maintenance | $11,305 | $800 |
$2,505
187,866
kWh
|
- | - | $8,800 | - | |
04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,824 | - | - | - |
$4,824
-
lb
|
- | - | |
05 | 4.122: Develop standard procedures to improve internal yields | $62,180 | $300 | - | - | - | - | $62,180 | |
TOTAL RECOMMENDED | $80,022 | $1,251 |
$3,562
222,450
kWh
|
$656
-
kW-mo/yr
|
$4,824
-
lb
|
$8,800 | $62,180 | ||
TOTAL IMPLEMENTED | $62,180 | $300 | - | - | - | - | $62,180 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs