Assessment Year | 2005 |
---|---|
Principal Product | Cable Connectors / Filters |
NAICS | 332721: Precision Turned Product Manufacturing |
SIC | 3451: Screw Machine Products |
Sales Range | $50 M to 100M |
# of Employees | 490 |
Plant Area |
106,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $499,528 | 6,598,400 |
kWh
|
$0.076 |
Electricity Demand | $190,650 | 13,476 |
kW-mo/yr
|
$14.15 |
Electricity Fees | $15,152 | - |
|
- |
Natural Gas | $68,915 | 8,884 |
MMBtu
|
$7.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,838,514 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,838,514 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $1,378 | - | - | - | $1,378 | - | |
02 | 2.4224: Upgrade controls on compressors | $31,676 | $40,711 |
$18,262
240,296
kWh
|
$13,414
-
kW-mo/yr
|
- | - | |
03 | 3.1191: Change procedures / equipment / operating conditions | $39,585 | $111,774 |
$13,113
172,536
kWh
|
$3,353
-
kW-mo/yr
|
$23,119 | - | |
04 | 3.2176: Increase use of automation | $1,765,875 | $3,500,000 |
$(-19,606.0)
(-257,982)
kWh
|
$(-5,009.0)
-
kW-mo/yr
|
$1,363,440 | $427,050 | |
TOTAL RECOMMENDED | $1,838,514 | $3,652,485 |
$11,769
154,850
kWh
|
$11,758
-
kW-mo/yr
|
$1,387,937 | $427,050 | ||
TOTAL IMPLEMENTED | $1,838,514 | $3,652,485 |
$11,769
154,850
kWh
|
$11,758
-
kW-mo/yr
|
$1,387,937 | $427,050 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs