ITAC Assessment: SU0218
ITAC logo
ITAC Assessment: SU0218
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Bare & Tinned Copper Wire & Cable
NAICS 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $50
M
to 100
M
# of Employees 302
Plant Area 326,000
ft2
Annual Production 1,127,721,130
lb
Production Hrs. Annual 8,568
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,812,267 29,076,030
kWh
Electricity Fees $177,603 -
Fuel Oil #4 $144,623 20,418
MMBtu
Fuel Oil #6 $58,773 9,454
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $337,553 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $52,034

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Fuel Oil #4 Savings Fuel Oil #6 Savings Ancillary Material Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $34,927 - $34,927
563,342
kWh
- - - -
02 2.4314: Use synthetic lubricant $27,119 - $27,119
437,396
kWh
- - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $7,931 - $7,931
127,890
kWh
- - - -
04 2.1232: Keep boiler tubes clean $4,058 - - - $2,890
-
MMBtu
$1,168
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $5,622 $785 $5,622
90,657
kWh
- - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,117 $2,100 $6,117
98,658
kWh
- - - -
07 3.1191: Change procedures / equipment / operating conditions $169,409 $114,259 - - - - $169,409
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,280 $7,100 $8,280
133,555
kWh
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,729 $1,878 $494
7,970
kWh
- - - $1,235
10 2.2414: Use waste heat from hot flue gases to preheat $13,025 $15,000 - - $9,257
-
MMBtu
$3,768
-
MMBtu
-
11 2.7314: Reduce ventilation air $14,692 $17,995 $14,692
236,963
kWh
- - - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $25,220 $53,200 $25,220
406,774
kWh
- - - -
13 2.6211: Conserve energy by efficient use of vending machines $456 $1,166 $456
7,358
kWh
- - - -
14 2.3212: Optimize plant power factor $18,968 $61,178 - $18,968 - - -
TOTAL RECOMMENDED $337,553 $274,661 $130,858
2,110,563
kWh
$18,968 $12,147
-
MMBtu
$4,936
-
MMBtu
$170,644
TOTAL IMPLEMENTED $52,034 $118,356 $31,831
513,402
kWh
$18,968 - - $1,235
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Fuel Oil #4 Savings Fuel Oil #6 Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs