Assessment Year | 2005 |
---|---|
Principal Product | Corrugated sheets and boxes |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
227,246
ft2
|
Annual Production | 53,148,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $372,598 | 4,715,200 |
kWh
|
$0.079 |
Electricity Demand | $173,307 | 13,657 |
kW-mo/yr
|
$12.69 |
Electricity Fees | $27,166 | - |
|
- |
Natural Gas | $322,740 | 53,327 |
MMBtu
|
$6.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,587 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,380 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $18,867 | - | - | - | - | - | $18,867 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $16,273 | - |
$12,225
154,744
kWh
|
$4,048
-
kW-mo/yr
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,819 | - |
$6,418
81,244
kWh
|
$3,401
-
kW-mo/yr
|
- | - | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,785 | $500 | - | - | - |
$10,785
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,763 | $954 |
$5,834
73,848
kWh
|
$1,929
-
kW-mo/yr
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $7,934 | $652 |
$5,967
75,537
kWh
|
$1,967
-
kW-mo/yr
|
- | - | - | |
07 | 2.2441: Preheat boiler makeup water with waste process heat | $6,167 | $2,280 | - | - | - |
$6,167
-
MMBtu
|
- | |
08 | 2.3212: Optimize plant power factor | $3,979 | $14,487 | - | - | $3,979 | - | - | |
TOTAL RECOMMENDED | $81,587 | $18,873 |
$30,444
385,373
kWh
|
$11,345
-
kW-mo/yr
|
$3,979 |
$16,952
-
MMBtu
|
$18,867 | ||
TOTAL IMPLEMENTED | $57,380 | $18,221 |
$12,252
155,092
kWh
|
$5,330
-
kW-mo/yr
|
$3,979 |
$16,952
-
MMBtu
|
$18,867 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs