ITAC Assessment: SU0215
ITAC logo
ITAC Assessment: SU0215
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Concrete Block
NAICS 327331: Concrete Block and Brick Manufacturing
SIC 3271: Concrete Block and Brick
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area 40,249
ft2
Annual Production 8,500,000
pieces
Production Hrs. Annual 3,120
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,705 681,473
kWh
Electricity Demand $48,283 3,742
kW-mo/yr
Electricity Fees $5,089 -
Natural Gas $49,195 6,519
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,975 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,926

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,049 - $1,133
12,314
kWh
$916
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,264 - $903
9,818
kWh
$361
-
kW-mo/yr
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,058 - $684
7,433
kWh
$374
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,712 $488 $2,641
28,704
kWh
$1,071
-
kW-mo/yr
05 2.4314: Use synthetic lubricant $1,814 $1,000 $1,182
12,852
kWh
$632
-
kW-mo/yr
06 2.4221: Install compressor air intakes in coolest locations $1,078 $579 $691
7,509
kWh
$387
-
kW-mo/yr
TOTAL RECOMMENDED $10,975 $2,067 $7,234
78,630
kWh
$3,741
-
kW-mo/yr
TOTAL IMPLEMENTED $8,926 $2,067 $6,101
66,316
kWh
$2,825
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs