| Assessment Year | 2005 |
|---|---|
| Principal Product | Rolls of Paper |
| NAICS | 322121: Paper (except Newsprint) Mills |
| SIC | 2621: Paper Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
110,000
ft2
|
| Annual Production | 36,015
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,072,059 | 16,271,793 |
kWh
|
$0.066 |
| Electricity Demand | $175,965 | 63,904 |
kW-mo/yr
|
$2.75 |
| Electricity Fees | $83,200 | - |
|
- |
| Natural Gas | $1,737,887 | 240,782 |
MMBtu
|
$7.22 |
| Fuel Oil #6 | $330,212 | 65,868 |
MMBtu
|
$5.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $362,673 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $361,340 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $65,094 | - | - | - | - | - | $65,094 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,343 | - |
$8,840
133,939
kWh
|
$503
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,021 | - |
$3,804
57,641
kWh
|
$217
-
kW-mo/yr
|
- | - | - | |
| 04 | 4.821: Pay bills on time to avoid late fees | $3,146 | - | - | - | - | - | $3,146 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $977 | - |
$925
14,016
kWh
|
$52
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4314: Use synthetic lubricant | $23,908 | $1,000 |
$22,618
342,696
kWh
|
$1,290
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,469 | $901 |
$5,175
78,402
kWh
|
$294
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $2,629 | $494 |
$2,486
37,668
kWh
|
$143
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.2136: Install / repair insulation on steam lines | $22,902 | $5,674 | - | - |
$22,902
-
MMBtu
|
- | - | |
| 10 | 2.2442: Preheat combustion air with waste heat | $70,404 | $35,100 | - | - |
$70,404
-
MMBtu
|
- | - | |
| 11 | 2.7135: Install occupancy sensors | $694 | $381 |
$694
10,512
kWh
|
- | - | - | - | |
| 12 | 2.2414: Use waste heat from hot flue gases to preheat | $153,447 | $120,000 | - | - |
$153,447
-
MMBtu
|
- | - | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $345 | $446 |
$113
1,717
kWh
|
$5
-
kW-mo/yr
|
- | $227 | - | |
| 14 | 2.6211: Conserve energy by efficient use of vending machines | $294 | $676 |
$278
4,205
kWh
|
$16
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $362,673 | $164,672 |
$44,933
680,796
kWh
|
$2,520
-
kW-mo/yr
|
$246,753
-
MMBtu
|
$227 | $68,240 | ||
| TOTAL IMPLEMENTED | $361,340 | $163,169 |
$43,848
664,362
kWh
|
$2,499
-
kW-mo/yr
|
$246,753
-
MMBtu
|
- | $68,240 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs