ITAC Assessment: SU0213
ITAC logo
ITAC Assessment: SU0213
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Rolls of Paper
NAICS 322121: Paper (except Newsprint) Mills
SIC 2621: Paper Mills
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 110,000
ft2
Annual Production 36,015
ton
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,072,059 16,271,793
kWh
Electricity Demand $175,965 63,904
kW-mo/yr
Electricity Fees $83,200 -
Natural Gas $1,737,887 240,782
MMBtu
Fuel Oil #6 $330,212 65,868
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $362,673 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $361,340

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $65,094 - - - - - $65,094
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,343 - $8,840
133,939
kWh
$503
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $4,021 - $3,804
57,641
kWh
$217
-
kW-mo/yr
- - -
04 4.821: Pay bills on time to avoid late fees $3,146 - - - - - $3,146
05 2.7142: Utilize higher efficiency lamps and/or ballasts $977 - $925
14,016
kWh
$52
-
kW-mo/yr
- - -
06 2.4314: Use synthetic lubricant $23,908 $1,000 $22,618
342,696
kWh
$1,290
-
kW-mo/yr
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,469 $901 $5,175
78,402
kWh
$294
-
kW-mo/yr
- - -
08 2.4221: Install compressor air intakes in coolest locations $2,629 $494 $2,486
37,668
kWh
$143
-
kW-mo/yr
- - -
09 2.2136: Install / repair insulation on steam lines $22,902 $5,674 - - $22,902
-
MMBtu
- -
10 2.2442: Preheat combustion air with waste heat $70,404 $35,100 - - $70,404
-
MMBtu
- -
11 2.7135: Install occupancy sensors $694 $381 $694
10,512
kWh
- - - -
12 2.2414: Use waste heat from hot flue gases to preheat $153,447 $120,000 - - $153,447
-
MMBtu
- -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $345 $446 $113
1,717
kWh
$5
-
kW-mo/yr
- $227 -
14 2.6211: Conserve energy by efficient use of vending machines $294 $676 $278
4,205
kWh
$16
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $362,673 $164,672 $44,933
680,796
kWh
$2,520
-
kW-mo/yr
$246,753
-
MMBtu
$227 $68,240
TOTAL IMPLEMENTED $361,340 $163,169 $43,848
664,362
kWh
$2,499
-
kW-mo/yr
$246,753
-
MMBtu
- $68,240
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs