ITAC Assessment: SU0212
ITAC logo
ITAC Assessment: SU0212
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Thick Film Micro-Electronic Components
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 127
Plant Area 45,000
ft2
Annual Production 91,322
pieces
Production Hrs. Annual 4,284
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $173,621 2,023,504
kWh
Electricity Demand $53,139 3,904
kW-mo/yr
Electricity Fees $3,175 -
Natural Gas $36,676 3,834
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,934 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,200

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 4.821: Pay bills on time to avoid late fees $395 - - - - $395
02 2.4231: Reduce the pressure of compressed air to the minimum required $3,679 - $3,012
33,466
kWh
$667
-
kW-mo/yr
- -
03 2.4314: Use synthetic lubricant $375 - $307
3,407
kWh
$68
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $670 - $547
6,079
kWh
$123
-
kW-mo/yr
- -
05 2.1222: Install turbulators $985 $571 - - $985
-
MMBtu
-
06 2.4221: Install compressor air intakes in coolest locations $2,637 $1,889 $2,147
23,856
kWh
$490
-
kW-mo/yr
- -
07 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $12,179 $10,575 - - $12,179
-
MMBtu
-
08 2.7135: Install occupancy sensors $1,966 $2,792 $1,966
21,840
kWh
- - -
09 2.6211: Conserve energy by efficient use of vending machines $230 $383 $189
2,097
kWh
$41
-
kW-mo/yr
- -
10 2.7124: Make a practice of turning off lights when not needed $148 $527 $148
1,643
kWh
- - -
11 2.7314: Reduce ventilation air $3,820 $13,919 $3,738
41,539
kWh
$82
-
kW-mo/yr
- -
12 2.1311: Replace electrically-operated equipment with fossil fuel equipment $97,661 $114,600 $60,934
677,040
kWh
$12,657
-
kW-mo/yr
$34,903
-
MMBtu
$(-10,833.0)
13 3.1191: Change procedures / equipment / operating conditions $21,189 $111,859 - - - $21,189
TOTAL RECOMMENDED $145,934 $257,115 $72,988
810,967
kWh
$14,128
-
kW-mo/yr
$48,067
-
MMBtu
$10,751
TOTAL IMPLEMENTED $9,200 $5,208 $7,580
84,212
kWh
$1,225
-
kW-mo/yr
- $395
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs