Assessment Year | 2005 |
---|---|
Principal Product | Carbonated and non-carbonated beverages |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
440,000
ft2
|
Annual Production | 115,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $780,255 | 11,408,280 |
kWh
|
$0.068 |
Electricity Demand | $368,417 | 30,701 |
kW-mo/yr
|
$12.00 |
Natural Gas | $374,978 | 58,066 |
MMBtu
|
$6.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,225,454 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,335 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $15,784 | - |
$12,772
182,453
kWh
|
$3,012
-
kW-mo/yr
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,184 | - |
$5,816
83,081
kWh
|
$1,368
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,803 | $75 |
$1,455
20,787
kWh
|
$348
-
kW-mo/yr
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $11,271 | $560 |
$9,123
130,324
kWh
|
$2,148
-
kW-mo/yr
|
- | |
05 | 2.4314: Use synthetic lubricant | $5,926 | $1,000 |
$4,798
68,542
kWh
|
$1,128
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $822 | $1,010 |
$822
11,741
kWh
|
- | - | |
07 | 4.212: Adopt in-house material generation | $2,182,664 | $3,516,395 |
$(-351,012.0)
(-5,014,464)
kWh
|
$(-82,656.0)
-
kW-mo/yr
|
$2,616,332 | |
TOTAL RECOMMENDED | $2,225,454 | $3,519,040 |
$(-316,226.0)
(-4,517,536)
kWh
|
$(-74,652.0)
-
kW-mo/yr
|
$2,616,332 | ||
TOTAL IMPLEMENTED | $24,335 | $2,085 |
$19,847
283,523
kWh
|
$4,488
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs