Assessment Year | 2007 |
---|---|
Principal Product | vehicle floor liners |
NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
SIC | 3083: Laminated Plastics Plate, Sheet, and Profile Shapes |
Sales Range | $1 M to 5M |
# of Employees | 100 |
Plant Area |
160,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $275,180 | 4,744,800 |
kWh
|
$0.058 |
Electricity Demand | $40,019 | 14,478 |
kW-mo/yr
|
$2.76 |
Electricity Fees | $77,525 | - |
|
- |
Natural Gas | $2,748 | 409 |
MMBtu
|
$6.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,336 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,180 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30,095 | $79,680 |
$27,558
555,610
kWh
|
$2,537
-
kW-mo/yr
|
- | |
02 | 2.2437: Recover waste heat from equipment | $2,095 | $3,851 | - | - |
$2,095
-
MMBtu
|
|
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,664 | $275 | - |
$5,664
-
kW-mo/yr
|
- | |
04 | 2.4226: Use / purchase optimum sized compressor | $2,966 | $5,529 |
$1,361
27,440
kWh
|
$1,605
-
kW-mo/yr
|
- | |
05 | 2.2511: Insulate bare equipment | $2,516 | $3,910 |
$2,516
43,376
kWh
|
- | - | |
TOTAL RECOMMENDED | $43,336 | $93,245 |
$31,435
626,426
kWh
|
$9,806
-
kW-mo/yr
|
$2,095
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,180 | $4,185 |
$2,516
43,376
kWh
|
$5,664
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs