ITAC Assessment: SU0187
ITAC logo
ITAC Assessment: SU0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Marble and Wood Products
NAICS 326191: Plastics Plumbing Fixture Manufacturing
SIC 3088: Plastics Plumbing Fixtures
Sales Range $10
M
to 50
M
# of Employees 188
Plant Area 270,749
ft2
Annual Production 0
pieces
Production Hrs. Annual 4,394
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $104,323 1,827,968
kWh
Electricity Demand $53,476 7,018
kW-mo/yr
Electricity Fees $1,680 -
Natural Gas $50,244 5,818
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,844 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,223

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,725 - $1,613
28,299
kWh
$1,112
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,502 $350 $885
15,529
kWh
$617
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $513 $442 $300
5,269
kWh
$213
-
kW-mo/yr
-
04 2.2437: Recover waste heat from equipment $26,177 $53,000 - - $26,177
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,721 $10,129 $3,456
60,637
kWh
$1,265
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $1,206 $3,817 $749
13,141
kWh
$457
-
kW-mo/yr
-
TOTAL RECOMMENDED $36,844 $67,738 $7,003
122,875
kWh
$3,664
-
kW-mo/yr
$26,177
-
MMBtu
TOTAL IMPLEMENTED $6,223 $10,479 $4,341
76,166
kWh
$1,882
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs