| Assessment Year | 1988 |
|---|---|
| Principal Product | BODY FLUID COLLATING UNIT |
| NAICS |
n/a
|
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | $10 M to 50M |
| # of Employees | 500 |
| Plant Area |
n/a
|
| Annual Production | 29,000,000
pieces
|
| Production Hrs. Annual | 8,496
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $511,277 | 12,184,936 |
kWh
|
$0.042 |
| Natural Gas | $5,408 | 901 |
MMBtu
|
$6.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $38,463 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,073 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $6,480 | $5,500 |
$6,480
178,195
kWh
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $500 | - |
$500
13,482
kWh
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $3,300 | $7,900 | - |
$3,300
-
MMBtu
|
|
| 04 | 2.7231: Use radiant heater for spot heating | $9,900 | $5,000 | - |
$9,900
-
MMBtu
|
|
| 05 | 2.4133: Use most efficient type of electric motors | $4,520 | $5,557 |
$4,520
123,095
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $7,020 | - |
$7,020
192,849
kWh
|
- | |
| 07 | 2.7229: Air condition only space necessary | $6,100 | $6,000 |
$6,100
127,784
kWh
|
- | |
| 08 | 2.7261: Install timers and/or thermostats | $590 | $600 |
$530
19,343
kWh
|
$60
-
MMBtu
|
|
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $53 | $55 |
$53
1,465
kWh
|
- | |
| TOTAL RECOMMENDED | $38,463 | $30,612 |
$25,203
656,213
kWh
|
$13,260
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $18,073 | $11,112 |
$18,073
495,604
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs