ITAC Assessment: SU0179
ITAC logo
ITAC Assessment: SU0179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Newspapers
NAICS 511110: Newspaper Publishers
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $10
M
to 50
M
# of Employees 331
Plant Area 111,000
ft2
Annual Production 16,530,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,505 3,200,400
kWh
Electricity Demand $93,272 7,350
kW-mo/yr
Natural Gas $49,528 6,785
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,598 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $12,807 - - - - $12,807
02 2.7111: Reduce illumination to minimum necessary levels $543 - $353
4,106
kWh
$190
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,108 $6,327 $5,702
66,309
kWh
$2,406
-
kW-mo/yr
- -
04 2.4221: Install compressor air intakes in coolest locations $1,671 $2,665 $847
9,855
kWh
$824
-
kW-mo/yr
- -
05 2.3212: Optimize plant power factor $3,469 $6,227 - - $3,469 -
TOTAL RECOMMENDED $26,598 $15,219 $6,902
80,270
kWh
$3,420
-
kW-mo/yr
$3,469 $12,807
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs