ITAC Assessment: GT0960
ITAC logo
ITAC Assessment: GT0960
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Blended and Packaged Tea Products
NAICS 311920: Coffee and Tea Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 245,550
ft2
Annual Production 14,546,423
lb
Production Hrs. Annual 6,240
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $486,122 4,477,600
kWh
Natural Gas $23,115 3,693
MMBtu
TOTAL YEARLY COSTS $509,237
RECOMMENDED SAVINGS* $248,417 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,049

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $22,810 $1,850 $25,710
235,872
kWh
$(-2,900.0)
02 2.4231: Reduce the pressure of compressed air to the minimum required $7,573 $800 $7,573
69,473
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,666 $8,719 $2,666
24,461
kWh
-
04 2.2628: Utilize a less expensive cooling method $39,614 $149,000 $39,614
363,433
kWh
-
05 2.9114: Use solar heat to make electricty $175,754 $2,009,756 $175,754
1,618,845
kWh
-
TOTAL RECOMMENDED $248,417 $2,170,125 $251,317
2,312,084
kWh
$(-2,900.0)
TOTAL IMPLEMENTED $33,049 $11,369 $35,949
329,806
kWh
$(-2,900.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs